CHAPTER VIII
STANDARD COSTING AND VARIANCE ANALYSIS
Standard
costing is a very important system of cost control. Standard costing aims at
eliminating the wastage and increasing efficiency in performances through
setting up standards for production expenses and production performance.
STANDARD COST AND STANDARD COSTING
Standard
cost is a predetermined cost. It is a determination in advance of production,
of what should be the cost. When standard costs are used for the purposes of
cost-control, the technique is known as the standard costing.
Eric. L. Kohler
has defined standard cost as “Standard cost is a forecast or pre-determination
of what actual cost should be under projected conditions, serving as a cost
control and as a measure of production efficiency or standard of comparison
when ultimately aligned actual cost. It furnishes a medium by which the
effectiveness of current results can be measured and the responsibility for
deviations can be placed”.
The
main points in the above definitions are:
(i)
It is pre-determined calculation of what
cost ought to be specific working conditions.
(ii)
It is built up by correlating standard
quantity (of machine time, labour time and material) and forecast of future
market trend for price standards (i. e., prices for material, wage rates and
machine cost per hour etc.)
(iii)
It provides bases for control through
variance accounting.
(iv)
It provides bases for valuation of stock
and work-in-progress and in some cases for fixing selling price.
Standard
costing is the preparation of standard costs and applying them to measure the
variations from actual costs and analyzing the causes of variations with a view
to maintain maximum efficiency in production. It is a technique which uses
standards for cost and revenues for the purpose of control through variance
analysis.
From
the definition given above, it is clear that the technique of standard costing
may comprise:
(i)
Ascertainment of standard costs under
each element of cost i. e., material, labour and overhead.
(ii)
Measurement of actual costs.
(iii)
Comparison of the actual costs with the
standard cost to find out the variances.
(iv)
Analysis of variances for the purpose of
ascertainment of reasons of variances for taking the appropriate action where
necessary so that maximum efficiency may be achieved.
STANDARD COSTING AND BUDGETARY
CONTROL
Both
standard costing and budgetary achieve the same objective of maximum efficiency
and cost reduction by establishing predetermined standards, comparing actual
performance with the predetermined standards and taking corrective measures,
where necessary. Thus, although both are useful tools to the management in
controlling costs, they differ in the following respects:
1.
To be able to establish standard
costs, some form of budgeting is essential as there is the need to forecast the
level of output and prescribed set of working conditions in the periods in
which the standard costs are to be used. On the other hand, budgetary control
can be prepared on the basis of past figures adjusted to future trends. But to
get the best out of budgetary control, linking of budgetary control with
standard costing is recommended.
2.
Standards are based on technical
assessments whereas budgets are based on past actual adjusted to future trends.
3.
Budgetary control deals with the
operations of department of business as a whole while standard costing is
applied to manufacturing of a product, process or processes or providing a
service. Thus, budgetary control is extensive whereas standard costing is
intensive in its application. For example, budgets are prepared for different
functions of the business i. e., production, sales, purchases, cash etc.
Standard costs, on the other hand are complied for various elements of cost.
4.
Standards are set mainly for
production and production expenses where as budgets are complied for all items
of income and expenditure. Therefore, budgeting is a much broader function than
standard costing.
5.
Budgets set up maximum limits to
expenses above which the actual expenditure should not be normally exceed.
Standards set up targets which are to be attained by actual performance. Thus,
budgetary control lays emphasis on costs not exceeding the budgets and standard
costing gives importance to cost approaching the standard costs.
6.
Budgets are projection of final
accounts; standard costs are projection of cost accounts because budgetary
control adopts a more general approach of giving service to the management than
does standard costing. Final accounting, as we know, is concerned with the
overall efficiency of the business whereas cost accounting deals with
individual products, ascertain and controlling their costs. Standards cost aim
at efficiency at every point; so they are projection of cost accounts. On the
other hand, budgetary control aims at overall efficiency (i. e., efficiency of
the particular function such as sales function, purchase function, production
function etc); so it is a projection of financial accounts.
7.
In budgetary control, variances are
not revealed through the accounts but are revealed in total. But in standard
costing, variances are analyzed in detail according to their originating cases.
Thus, standard costing reveals variances through different accounts.
8.
Budgets are anticipated or expected
costs meant to be used for forecasting requirements of material, labour, cash
etc. standard costs, on the other hand, do not tell what the costs are expected
to be, but rather what the costs should be under specific conditions of
production performance and as such cannot be used for the purpose of
forecasting.
Both standard costing and budgetary control are
complimentary to each other and for maximum efficiency both should be used
simultaneously. Both may prove more effective if they are used in conjunction
with each other.
STANDARD COSTING AND MARGINAL
COSTING
Standard
costing is a system of accounting in which all expenses (fixed and variable)
are considered for the determination of standard cost for a prescribed set of
working conditions. On the other hand, marginal costing is a technique in which
only variable expenses are taken to ascertain the marginal costing is a
technique in which only variable expenses are taken to ascertain the marginal
cost. Both standard costing and marginal costing are completely independent and
each other and may be installed jointly. This system of joint installation may
be named as Marginal Standard Costing or Standard Marginal Costing System.
Variances are calculated in the same way as in standard costing system with the
only difference that the volume variances are absent because fixed expenses are
charged in totals in each period.
Preliminaries to the Establishment
of Standard Costs
The
following preliminaries should be gone through before a standard costing system
is established:
1.
Establishment of cost centers; 2.Type of standard; and 3. Setting the
standards.
1.
Establishment
of Cost Centers. As defined earlier in this book, a cost
centre is a location, person or item of equipment for which costs may be
ascertained and used for the purpose of the cost control. Establishment of cost
centers in necessary for fixing responsibilities for unfavorable variance.
2.
Types
of Standards. They are three types of standards:
a) Current standard.
A standard which is related to current conditions and is established for use
over a short period of time.
Ideal
Standard: This is a standard which can be attained under the
most favorable conditions possibly. In other words, this standard is based upon
a very high degree of efficiency which is rather impossible to achieve. In this
standard, it is assumed that there will be the most desirable conditions of
performance and that there will be no wastage of material or time and no
inefficiencies in the manufacturing processes. This standard is not likely to
be achieved because ideal conditions of performance will not prevail. It is,
therefore, a theoretical standard.
The
unity of this standard is that it sets a target which, though not attainable in
practice, is always aimed at. The criticism of the standard is that when actual
costs are compared with such standard costs, large unfavorable variances are
shown and these variances become a permanent feature of the concern. The ideal
standard will breed frustration among employees because such standard is never
to be attained. Nobody will pay serious attention to such standard and setting
up of this standard will become a farce.
Expected
or Attainable Standard: This is a standard which is
anticipated during a future specified budget period. In fixing this type of
standard present conditions and circumstances prevailing with in a particular
industry are taken into consideration. Beside due weight age is given to the
expected changes in the present circumstance and conditions. In setting up this
standard, a reasonable allowance is also made for unavoidable (normal)
wastages. This standard is, therefore, considered to be more realistic than the
ideal standard because this standard is based on the realities rather than on
the most ideal conditions. Hence, this type of standard is best suited from
control point of view because this standard reveals real variances from the
attainable performance.
b) Basic Standard.
It is a standard which is established for use unaltered over a long period of
time. This standard is fixed for long periods so as to help foreword planning.
Basic standard is established for some base year and is not changed for a long
period of time as material prices, labour rates and other expenses change.
Deviations of actual cost from basic standards will not serve any practical
purpose because basic standards remain unaltered over a long period of time and
are not adjusted to current market conditions. Thus, this type of standard is
not suitable from cost control point of view. However variances calculated on
the basis of basic standards will help in studying the trends in manufacturing
costs over a long period of time.
Comparison
of Current and Basic Standard Cost. Current standard
relate to current conditions and operate only for a short period before they
are revised when conditions change. On the other hand, basic standards are set
for a long period and there is no need for constant revision for such standards.
Deviation of actual costs from basic standard cost will not serve any practical
purpose because standards are not adjusted to current market conditions.
However such standards will be helpful in studying the trends of variance over
a long period of time which is not possible in case of current standards which
go on changing. Current standards will take care of inflationary tendencies
because they are adjusted to current market conditions. On the other hand,
basic standards are static and do not take care of inflationary tendencies.
c) Normal Standard.
This standard is defined as “the average standard which it is anticipated can
be attained over a future period of time, preferable long enough to cover one
trade cycle’. Such standards are established on the basis of average estimated
performance over a future period of time (say 5 years) covering one trade
cycle. It is difficult to follow normal standards in practice as it is not
possible to forecast performance with a reasonable degree of accuracy for a long
period of time. Such standards are attainable under anticipated normal
conditions and are not attainable if anticipated conditions do not prevail over
a future period of time. That is why; normal standards may not be a useful
device for a purpose of cost control.
3.
Developing
or Setting the Standards or Establishment of Standard Cost.
Just like a budget committee, there should be Standard Committee which should
be entrusted with the work of setting standard costs. The committee will
include General Manager, Purchase Officer, Production Engineer, Production
Manager, Sales Manager, Cost Account, and other functional heads, if any.
Of all the persons, the cost accountant
plays a very important role in setting the standards because he is to supply
the necessary costs figures and coordinate the activities of the committee so
that standards set are as accurate as possible.
It may be noted that standards set
should neither be too high nor too low. Nobody will take interest in the
standards if these are too high because such standards are not capable of being
achieved and employees will always have an opportunity to excuse the failure to
reach standards. Such standards are not realistic and, therefore, cannot be
used in inventory valuation, product costing and pricing, planning and control,
and capital investment decisions. Low standards, on the other hand, will not
induce employees and management to put more efforts because they can be
achieved very easily. They defeat the objectives of standard costing and fail o
disclose inefficiencies because they can be attained by poor performance. As a
general rule, currently attainable standards should be set which can be
attained if employees and management become more efficient or put some more
efforts. Such standards motivate employees and are most appropriate for
performance appraisal, cost control and decision making.
According to the National Association of
Accountants (U.S.A) “Such standards provide definite goals which employees can
usually be expected to reach and also appear to be fair bases from which to
measure deviations for which the employees are held responsible. A standard set
at a level which is high at still attainable with reasonable diligent effort
and attentive to the correct methods of doing the job may also be effective for
stimulating efficiency”.
The success of standard costing depends
upon the establishment of correct standards. Thus, every possible care should
be taken in the establishment of standard and standards should be established
for each element of cost as follows:
(a) Direct Material Cost.
Standard material cost for each product should be predetermined. This will be
include:
(i)
Determination of standard quantity of
materials needed for the production.
(ii)
Determination of standard price per unit
of material.
In
ascertaining standard quantity of materials, the standard specification, of
materials should be planned by the engineering department after consulting the
past records. While setting standards an allowance should be made for the
normal wastage of materials. The purpose of determining standard quantities of
materials should be to achieve maximum economies in material usage.
The
standard prices of materials should be determined for the various types of
material needed for the production. This is done by the cost accountant in
collaboration with the purchase officer. Standard price for each item of
material is established after carefully studying the market conditions and
forecasting the trend of prices for a future period. While setting standard material
price, the cost of purchasing and storekeeping should also be include in the
price of materials. The object of fixing standard price of materials is to
increase efficiency in the purchasing so that price of materials may be kept
down. Any difference between standard price and actual; price is to be referred
to the Purchasing Department of explanation, so before setting standards for
material price, it is advisable to see hat purchasing functions are efficiently
managed.
Setting
up of standard price of materials required is a difficult task because it
depends on so many factors beyond anybody’s control. Generally standard prices
are based on current price adjusted to expected changes in future.
(b) Direct Labour Cost.
Determination of standard direct labour cost will include determination of:
(i)
Standard time
(ii)
Standard rate
It
become necessary to standardize the time to be taken for each category of
labour and for each operation involved. Time and motion study will determine
how much time is to be allowed for each operation involved while fixing the
standard time to be taken for each category for labour and for each operation
involved. While fixing the standard time, due allowance should be made for
fatigue, tool setting, receiving instructions and normal idle time. Standard time can also be determined on the
basis of average of the past performance. Though this method is simple, it is
not scientific. Thus standard time is established on the basis of time and
motion study and this is done in conjunction with the work study engineers.
Standard time established according to time and motion study are independent of
previous performances. It is good for the development of objective standards.
Standard time can also be set by taking trial runs for new products. This method
is not satisfactory as real conditions are not available in such runs.
The
fixation of standard labour rates is not so difficult as the fixation of
standard prices of materials is because labour rates are usually
pre-established. Standard rates of pay should be established for every category
of labour. Labour rates in the past may not be reliable basis for determination
of rates if the labour rates are subject to fluctuating demand and supply of
the labour force. Any expected increase in rates should be considered in the
determination of standard rates. Establishment of standard rates of pay do not
present any problem in those industries where wage rates have been fixed by
contracts, Law, Wages Tribunals and Wages Boards. Fixation of standard rates will
depend upon the method of wage payment. Standard rates per hour or pay day will
be fixed in wages are paid according to time wages system and when the method
of wage payment is piece rate, standard wage per piece will be fixed. Personal
department will help the cost accountant in determining standard rates of pay.
Overheads:
Broadly speaking overheads are segregated into fixed and variable and standard
overhead rate should be determined for fixed as well as variable overhead.
Standard fixed overhead rates and standard variable overhead rate should also
be determined according to the function –wise classification of
overheads-manufacturing, administrative and selling and distribution so that
exact place of overhead variance may be located and corrective action may be
taken. Standard overhead rate is determined keeping in view past experience,
present conditions and future trends. Fixation of standard overhead rate
involves determination of standard overhead costs, estimation of standard level
of production reduced to a common base such as unit of production, direct
labour hours, machine hours, etc. and finally determination of standard
overhead rate by dividing standard overhead costs by standard level of
production. The formula for the calculation of standard rate is:
Standard
variable overhead rate: Standard
variable overheads for the budget period
Budget
production in units or budgeted hours for the budget period
Standard
fixed overhead rate: Standard
fixed overheads for the budget period
Budget
production in units or budgeted hours for the budget period
Standard Hours
Production is generally expressed in
physical units such kilos, tons, gallons, units, dozens etc. but it is
difficult to express all the products in one common unit when different types
of products which are measured in different units are manufactured in a
factory. In such a case, it is essential to have a common unit in which all the
products can be measured. Time factor is common to all the products, and,
therefore, production can be expressed in standard hours. A standard hour can
be defined as an hour which measures the amount of work that should be
performed in one hour under standard conditions.
ANALYSIS OF VARIANCES
Control
is a very important function of management. Through control management ensures
that performance of the organization conforms to its plans and objectives.
Analysis
of variances is helpful in controlling the performance and achieving the
profits that have been planned.
The deviation of the actual cost of
profit or sales from the standard cost or profit or sales is known as “variance”.
When actual cost is less than standard cost or actual profit is better than
standard profit, it is known as favorable variance and such a variance is
usually a sign of efficiency of the organization. On the other hand, when
actual cost is more than standard cost or actual profit or turnover is less
than standard profit or turnover, it is called unfavorable or adverse variance
and usually an indicator of inefficiency of the organization. The favorable and
unfavorable variances are also known as credit and debit variances
respectively. Variances of different items of cost provide the key to cost
control because they disclose whether and to what extent standards set have
been achieved.
Another way of classifying the
variance may be controlled and uncontrollable variances. If a variance is due
to inefficiency of a cost centre (i. e., individual or department), it is said
to be controllable variance. Such a variance can be corrected by taking a
suitable action. For example, if actual quantity of material used is more than
the standard quantity, the foreman concerned would be responsible for it. But
if excessive use is due to defective supply or materials or wrong setting of
standards, the purchasing department or cost accounting department would be
responsible for it. On the other hand, an uncontrollable variance does not
relate to an individual or department but it arise due to external reasons like
increase in price of materials. This type of variance is not controllable and
no particular individual can be held responsible for it.
There are a number of reasons which
gives rise to variances and the analysis of variances will help to locate the
reason and person or department responsible for a particular variance. The
management need not pay attention to items or departments proceeding according
to standards laid down. It is only in case of unfavorable items that the
management has to exercise control. This type of management technique is known
as ‘management by exception’. This type of technique is considered as an
efficient way of exercising control because management cannot devote their
limited time to every item.
The deviation of total actual cost
from total standard cost is known as total cost variance. It is a net variance
which is the aggregate of all variance relating to various elements of cost, both
favorable and unfavorable.
Analysis of variances may be done in
respect of each element of cost and sales, viz.,
1. Direct
Material Variances
2. Direct
Labour Variances
3. Overhead
Variances
4. Sales
Variances
Material Variances
In case of materials, the following
may be the variance:
(a) Material
Cost Variance
(b) Material
Price Variance
(c) Material
Usage or Quantity Variance
(d) Material
Mix Variance
(e) Material
Yield Variance
The
following chart shows the division and sub-division of material variances:
Material Cost Variance
Material
Price Variance Material
Usage or Quantity Variance
Material Mix Variance Material
Yield Variance
Now,
we proceed to define these variances one by one.
(a) Material Cost Variance (MCV).
It is the difference between the standard cost of materials allowed (as per
standards laid down) for the output achieved and the actual cost of material
used. Thus, it may be expressed as:
Material
Cost Variance = Standard Cost of Materials for Actual Output – Actual Cost of Material
Used
Or
Material Cost Variance = Material Price Variance + Material Usage or Quantity
Variance
Or
Material Cost Variance = Material Price Variance +Material Mix Variance + Material
Yield Variance
In
order to calculate material cost variance, it is necessary to know:
1. Standard
quantity of materials which should have been required (as per standards set) to
produce actual output. Thus, standard quantity of materials is :
Actual
Output x Standard Quantity of Materials per unit.
Note.
In order to find out standard quantity of materials specified, actual output
(and not standard output) is to be multiplied by standard quantity of materials
per unit.
2. Standard
price per unit of materials
3. Actual
quantity of materials used
4. Actual
price per unit of materials
(b) Material Price Variance (MPV).
It is that that portion of the material cost variance which is due to the difference
between the standard cost of materials used for the output achieved and the
actual cost of materials used. In other words, it can be expressed as:
Material
Price Variance:
Actual
usage (Standard Unit Price – Actual Unit Price)
Here,
Actual Usage = Actual Quantity of
material (in units) used
Standard
Unit Price = Standard price of material
per unit
Actual
Unit Price = Actual price of
material per unit
(c) Material Usage (or Quantity)
Variance (MQV). It is that portion of the material cost
variance which is due to the difference between the standard quantity of
materials specified for the actual output and the actual quantity of material
used. It may be expressed as:
Material
Usage Variance:
Standard
Price per unit (Standard Quantity – Actual Quantity)
(d) Material Mix Variance (MMV).
It is that portion of the material usage variance which is due to the
difference between standard and the actual composition of a mixture. In other
words, this variance arises because the ratio of materials being changed from the
standard ratio set. It is calculated as the difference between the standard
price of standard mix and standard price of actual mix.
In
case of material mix variance, two situations may arise:
(i)
Actual weight of mix and the standard
weight of mix do not differ. In such a case, material mix variance is
calculated with the help of the following formula:
Standard
Unit Cost (Standard Quantity – Actual Quantity)
Or
Standard Cost of Standard Mix – Standard Cost of Actual Mix
If
the standard is revised due to shortage of a particular type of material, the
material mix variance is calculated as follows:
Standard
Unit Cost (Revised Standard Quantity – Actual Quantity)
Or
Standard Cost of Revised Standard Mix – Standard Cost of Actual Mix
(e) Material Yield (or Sub-usage)
Variance (MYV). It is that portion of the material
usage variance which is due to the difference between the standard yield
specified and the actual yield obtained. This variance measures the abnormal
loss or saving of materials. This variance is particularly important in case of
process industries where certain percentage of loss of materials is inevitable.
If the actual loss of materials differs from the standard loss of materials,
yield variance will arise. Yield variance is also known as scrap variance. This
loss may result in the following two situations:
i)
When standard and actual mix do not
differ. In such a case, yield variance is calculated with the help of the
following formula:
Yield Variance =
Standard Rate (Actual Yield – Standard Yield)
Where, Standard Rate = Standard Cost of Standard Mix
Net
St. Output (i. e, Gross Output – St. Loss)
ii)
When actual mix differs from standard
mix. In such a case, formula for the calculation of yield variance is almost
the same. But since the weight of actual mix differs from that of the standard
mix, a revised standard mix is to be calculated to adjust the standard mix in
proportion to the actual mix and the standard rate is to be calculated from the
revised standard mix as follows:
Standard Rate = Standard Cost of Revised Standard Mix
Net standard
Output
Formula for yield variance in such a case is :
Yield Variance = Standard Rate (Actual Yield – Revised Standard Yield)
Labour Variances
Labour
variances can be analyzed as follows:
a) Labour
Cost Variance(LCV)
b) Labour
Rate (of Pay) Variance (LRV)
c) Total
Labour Efficiency Variance (TLEV)
d) Labour
Efficiency Variance (LEV)
e) Labour
Idle Time Variance (LITV)
f) Labour
Mix Variance or Gang Composition Variance (LMV or GCV)
g) Labour
Yield Variance or Labour Efficiency Sub-variance (LYV or LESV)
h) Substitution
Variance.
These
variance are like material variance and can be defined as follows:
a) Labour Cost Variance.
It is the difference between the standard cost of labour allowed (as per standard laid down) for the actual output
achieved and the actual cost of labour employed. It is also known as wages
variance. This variance is expressed as:
Labour
Cost Variance = Standard Cost of Labour – Actual Cost of Labour
b) Labour Rate (of Pay) Variance. It
is that portion of the labour cost variance which arises due to the difference
between the standard rate specified and the actual rate paid. It is calculated
as follows:
Rate
of Pay Variance = Actual Time Taken (Standard Rate – Actual Rate)
c) Total Labour Efficiency Variance.
It is that part of labour cost variance which arises due to the difference
between standard labour costs of standard time for actual time paid for. It is
calculated as follows:
Total
Labour Efficiency Variance (TLEV) = Standard Rate (Standard time for Actual Output
– Actual Time Paid for)
Total
labour efficiency variance is calculated only when there is abnormal idle time.
d) Labour Efficiency Variance.
It is that portion of labour cost variance which arise due to the difference
between the standard labour hours specified for the output achieved and the
actual labour hours spent. It is expressed as:
Labour
Efficiency Variance = Standard Rate (standard Time for Actual output – Actual
Time Worked). Hence standard time for actual output means time which should be
allowed for the actual output achieved.
Actual
time worked means actual labour hours spent minus abnormal idle hours.
e) Labour Idle Time Variance.
It is calculated only when there is abnormal idle time. It is that portion of
labour cost variance which is due to the abnormal idle time of workers. This
variance is shown separately to show the effect of abnormal cases affecting
production like power failure, breakdown of machinery shortage of materials
etc. while calculating labour efficiency variance, abnormal idle time is
deducted from actual time expended to ascertain the real efficiency of the
workers. Labour idle time variance is expressed as :
Idle
Tine Variance = abnormal Idle Time X Standard Rate
Total
Labour Cost Variance = Labour Rate of Pay Variance + Total Labour Efficiency
Variance
Total
Labour Efficiency Variance = Labour Efficiency Variance + Labour Idle Time
Variance
f) Labour
Yield Variance. It is like material yield variance and arises due to the
difference between yield that should have been obtained by actual time utilized
on production and actual yield obtained. It can be calculated as follows:
Standard
labour cost per unit (Actual Yield in units – Standard Yield in units expected
from the actual time worked on production).
g) Substitution Variance. This
is a variance in labour cost which arises due to substitution of labour when
one grade of labour is substituted by another. This is denoted by difference
between the actual hours at standard rate of standard worker and the actual
hours at standard rate of actual worker. This can be denoted as under:
Substitution
variance = (Actual hours X std. rate of std. worker) – Actual hours X Std rate
for actual worker)
OVERHEAD VARIANCE
Overhead cost variance can be
defined as the difference between the standard cost of overhead allowed for the
actual output achieved and the actual overhead cost incurred. In other words,
overhead cost variance is under or over absorption of overheads. The formula
for the calculation is:
Overhead cost variance
Actual
output X Standard Overhead Rate per Unit – Actual Overhead Cost or Standard
Hours for Actual Output X standard Overhead Rate per hour – Actual Overhead
Cost
Overhead
cost variance can be classified as :
(1) Variable
Overhead Variance
(2) Fixed
Overhead Variance
1. Variable Overhead Variance.
It is the difference between the standard variable overhead cost allowed for
the actual output achieved and the actual variable overhead cost. This variance
is represented by expenditure variance only because variable overhead cost will
vary in proportion to production so that only a change in expenditure can cause
such variance. It is expressed as:
Actual
output X standard variable overhead rate – Actual variable overheads or St.
Hours for actual output X St. Variable overhead rate per hour – Actual variable
overheads
Some
accountants also find out variable overhead efficiency variance just like
labour efficiency variance. Variable overhead efficiency variance can be
calculated if information relating to actual time taken and time allowed is
given. In such a case variable overhead variance can be divided into two part
as given below:
a) Variable
overhead expenditure variance = actual hours worked X standard variable
overhead rate per hour – actual variable overhead
Or
actual hours (Standard variable overhead rate per hour – actual variable
overhead rate per hour
Variable
overhead expenditure variance is calculated in the same way as labour rate
variance is calculated.
b) Variable
overhead efficiency variance = standard time for actual production X
standard variable overhead rate per hour
– actual hours worked X standard variable overhead rate per hour
Or
standard variable overhead rate per hour (standard hours for actual production
actual hours)
Variable
overhead efficiency variance resembles labour efficiency variance and
calculated like labour efficiency variance.
2. Fixed overhead variance.
It is that portion of total overhead cost variance which is due to the
difference between the standard cost of fixed overhead allowed for the actual
output achieved and the actual fixed overhead cost incurred. The formula for
the calculation of the variance is
Actual
output X standard fixed overhead rate per unit – Actual fixed overheads
Or
standard hours produced X standard fixed
overhead rate per hour – Actual fixed overheads
(Standard
hours produced = time which should be taken for actual output i. e., standard
time for actual output)
This
variance is further analysed as under:
1.
Expenditure
variance: It is that portion of the fixed overhead variance
which is due to the difference between the budgeted fixed overheads and the
actual fixed overheads incurred during a particular period. It is expressed as:
Expenditure
variance = budgeted fixed overheads – actual fixed overheads
Expenditure
variance = budgeted hours X standard fixed overhead rate per hour – actual
fixed overheads.
2.
Volume
variance: It is that portion of the fixed overhead variance
which arises due to the difference between the standard cost of fixed overhead
allowed for the actual output and the budgeted fixed overheads for the period
during which the actual output has been achieved. This variance shows the over
or under absorption of fixed overheads during a particular period. If the
actual output is more than the budgeted output, there is over-recovery of fixed
overheads and volume variance is favourable and vice versa if the actual output
is less than the budged output. This is so because fixed are not expected to
change with the change in output. This variance is expected as:
Volume
variance = actual output X standard rate – budgeted fixed overheads
Or
standard rate (Actual output – budgeted output)
Or
Volume variance = standard rate per hour (standard hours produced – actual
hours)
Standards
hours produced means number of hours which should have been taken for the
actual output as per the standard laid down.
i) Capacity
variance. It is that portion of the volume variance which is due to working
at higher or lower capacity
than the budgeted capacity. In other word , this variance is related to the
under and over utilization of plant and equipment and arises due to idle time,
strikes and lock-output, breakdown of the machinery, power failure, shortage of
materials and labour, absenteeism, overtime, changes in number of shifts. In
short, the variance arises due to more or less working hours than the budgeted
working hours. It is expressed as:
Capacity
variance = standard rate ((revised budgeted units – budgeted units)
Or
capacity variance = standard rate (revised budgeted hours – budgeted hours)
ii) Calendar
Variance. It is that portion of the volume variance which is due to the
difference between the number of working days in the budget period and number
of actual working days in the period to which the budget is applicable. If the
actual working days are more than the standard working days, the variance will
be favorable and vice versa if the actual working days are less than the
standard days. It is calculated as:
Calendar
variance = Increase or decrease in production due to more or less working days
the rate of budgeted capacity X standard rate per unit.
iii)
Efficiency
Variance. It is that portion of the volume variance which is
due to the difference between the budgeted efficiency of production and the
actual efficiency achieved. This variance is related to the efficiency of
workers and plant and is calculated as:
Standard
rate per unit (Actual production (in units0 – standard production (in units))
Or
standard rate per hour (standard hours
produced – actual hours)
Here, standard production or hours means
budgeted production or hours adjusted to increase or decrease in production due
to capacity or calendar variance.
Two Variance and Three Variance
Methods of Analysis of Overhead Variance
Analysis
of overhead variance can also be made by two variance and three variance
methods. The analysis of overhead variances by expenditure and volume is called
two variance analysis. When the volume is further analysed to know the reasons
of change in output, it is called three variance analysis. Change in output
occurs due to:
i) Change in capacity i. e., change in
work in hours per day giving rise to capacity variance.
ii) Change in number of working days giving
rise to calendar variance.
iii) Change in the level of efficiency
resulting into efficiency variance.
Thus,
three variance analysis includes:
i) Expenditure variance
ii) Volume variance further analysed into
a) Capacity
variance b) Calendar variance, and c)
Efficiency variance
No comments:
Post a Comment